Debugging Scheme of DCS System-Check Before Power On

source:   2019-08-13   browse:1136

Debugging Scheme of DCS System-Check Before Power On


Abstract:


Field debugging is mainly to check the use of system software, and the application software configuration confirmation and functional testing. In this paper, the relevant debugging scheme and steps of DCS system are described in detail.


Field debugging is mainly to check the use of system software, and the application software configuration confirmation and functional testing.


Today, Introducing what to do before the power on:


Cable insulation resistance meets the requirements (more than 5M euro), check the cable insulation resistance test record, and spot check the actual measurement if necessary.


Check that all power lines, signal lines and communication buses are connected correctly.

The model and position of each frame card, adapter and its interface in the control station, operation station and engineer station are correct.

The preset knob of each card is in the correct position.


The power supply unit and the power switch on the card are all in the "OFF" position, and all fuses are intact.

Grounding resistance test for grounding system:


A. Remove the "MG" and "CG" grounding bus from the ground floor of the control room, and use the grounding resistance tester to measure the base grounding resistance respectively, which shall meet the design requirements (less than 10 euros).

B. Use multimeter to check whether the grounding bus bar of each cabinet is connected with "MG" and "CG" grounding plates respectively.

C. The insulation resistance measured between "MG" and "CG" shall meet the requirements of gbj93-86 specification (more than 5M euro).


UPS power supply testing:


A. Check that the power panel and the power switch are in the "OFF" position.

B. Check that the power panel and the power switch are in the "OFF" position.The electrical personnel will put the UPS into operation. The voltage before the measurement is sent to the main power switch of the power panel of the instrument should be 220VAC±10% and 50Hz±2%.

C. UPS uninterrupted test by electrical personnel.(repeat the test after the full load is used, and the battery power supply time should not be less than 30 minutes)


Today's Recommendation (DCS TMR Triconex Module) :


Visit our website for more detail: https://www.cambiautomation.com/

Or contact Unik, sales5@cambia.cn , for any questions.


Triconex 3805ENTriconex 3601TRICONEX TRICON 3604ETriconex 9662-110
Triconex 3805ETriconex 3511Triconex TCM 4353Triconex 9662
Triconex 3708ETriconex 3510TRICONEX NCM4320Triconex 9563-810
Triconex 3706ATriconex 3504ETRICONEX ICM4101Triconex 9563
Triconex 3704ETriconex 3503ETriconex HCU3700/3703ETriconex 9000011-000
Triconex 3703ETriconex 3502ETriconex FSDO 7400159-030Triconex 8312
Triconex 3700ATriconex 3501TTriconex EMPII3006Triconex 8311
TRICONEX 3700Triconex 3501ETRICONEX EICM2 EICM 4118 7400145-100Triconex 8310
Triconex 3664Triconex 3501Triconex EICM2 7400145-200TRICONEX 8305A
TRICONEX 3636RTriconex 3351Triconex EICM 4107TRICONEX 8305
Triconex 3625Triconex 3301Triconex DI3301Triconex 8300A
Triconex 3624Triconex 3008Triconex AI3351Triconex 8300
TRICONEX 3615ETriconex 3006 EMPIITriconex 9853-610Triconex 8111
Triconex 3614ETriconex 3006Triconex 9760-210Triconex 8110
Triconex 3604ETRICONEX 3005Triconex 9753-110Triconex 4354
TRICONEX 3604ATRICONEX 3003-EMPIITriconex 9674-810Triconex 4351B
TRICONEX 3603BTriconex 3003 EMPIITriconex 9662-810Triconex 4351A
Triconex 3601ETriconex 3002Triconex 9662-610Triconex 4329

15591990640701230048.jpg